19.10.2021 100% Guarantee Over 20 years InCon KZ Team successfully repairs and constructs railways. For each performed scope of work we give an obligatory quality assurance ... Read more
15.10.2021 Roads to residential areas InCon KZ continues road construction works in new residential areas in Taldykorgan. The project launched last March, total length is 5.5 km To thi... Read more
16.03.2021 Start of new season We congratulate the team of Integra Construction KZ LLP with the start of track works in 2021. Today the first track possession has been successful... Read more
15.10.2020 The plan is completed 100%! Today at Apanovka – Kazanbassy station-to-station block, workers of the Northern Directorate have renewed 1241.7 m of track panel It was the final... Read more
01.10.2020 Track laying plan is fulfilled 95.7% In 6 months of track works InCon KZ Team has renewed 162 km of railways, 128 km of continuous welded rails have been changed Crushed-stone ballast... Read more
03.09.2020 The plan of August is fulfilled 100% InCon KZ team renewed 30.3 km of track in the last summer month Works included three sections: Passing loop 117 – Atassu and Kyzylzhar – Tuyemoyna... Read more
07.07.2020 Track rehabilitation in June Overall, 28 track possessions for track laying have been carried out in June by InCon KZ team. Works have been performed in Almaty, Kyzylorda and K... Read more