Construction of Roads in South-West Residential Area (microdistricts No. 8,9) Taldykorgan
Length – 5.6 km / Completion of construction: 2020-2025
Scope of work:
- Total road length – 5.6 km
- Main streets – 3.5 km;
- Local streets – 2.03 km;
- Road earthworks – 60.2 thou m³;
- Soil consolidation for road – 45.4 thou m³;
- Laying of sand and gravel mix for road – 75.1 thou m²;
- Laying of crushed stones with bitumen for road – 65.2 thou m²;
- Laying of black crushed-stone for road – 48.3 thou m²;
- Laying of asphalt concrete pavement – 48.3 thou m².