The Head of State visited a new microdistrict under construction in the center of Zhetysu region to see the progress of construction on its territory.
Kassym-Jomart Tokayev was informed that 41 residential buildings are under construction in the microdistrict. According to Akim of Taldykorgan Yernat Bazil, last year 14 houses with 509 apartments with an area of 44.1 thousand square meters were commissioned in this area.By the end of this year, it is planned to complete the construction of 21 more houses for 783 apartments, in 2024 – the remaining 6 houses for 218 apartments.
In the near future, more than 28 thousand people, or 14% of the city's population, will become new settlers in new microdistricts.
It should be noted that Integra Construction KZ also contributes to the improvement of new microdistricts. The company is a general contractor for road construction in the southwestern residential area (No. 8 and No. 9).