In 6 months of track works InCon KZ Team has renewed 162 km of railways, 128 km of continuous welded rails have been changed
Crushed-stone ballasting amounted to 427 thous.m3
By efforts of the company directorates 107 track possessions was carried out in Almaty, Kyzylorda, Karaganda and Kostanay regions. Generally, this is the hard work of our track workers, organizers of work and everyday life at operation.
We are starting the final month of the season. In October, it is planned to complete the laying of track.