The first track possession was carried out at the section "Junction 17 - Junction 33 - Koktenkol" for the Zhanaarka track division, of the Karaganda division
In 7 hours 1.5 km of track panel was renewed. Congratulations to the branch team on a great start! In general, 27.3 km of the railway track will be renewed on this section.
In 2022, two branches of Integra Construction KZ have already begun work on the overhaul of railways in Kazakhstan. We are waiting for the start of the Northern Directorate!