The construction of the railway line bypassing Almaty continues
| News

The construction of the railway line bypassing Almaty continues


According to the project, by the end of 2025, it is planned to build 75 main and 8 km of station tracks, including bridges, overpasses and culverts.

Excavation work is 90% completed (5.79 million m³ out of 6.46 million m³).

Construction of 14 bridges was completed. 4 more bridges in operation (75%).

43 culverts were installed, 12 in progress (78%).

The reconstruction of the main gas pipeline is 100% complete.

The assembly of the rail-and-sleeper grid was 69 km out of 129.6 km (53%).

6 km of track from Zhetygen station has been laid.

The project is aimed at reducing the load on the railway junction of the city on the 40%, as well as reducing the delivery time of goods to 24 hours.