Starting track repair on new sections
| News

Starting track repair on new sections


May 25-29, team of the Western Directorate proceeded to work in two directions at once.

The first track possessions were conducted on sections:

  • Sagiz – Passing loop 265, with the length of 10 km for Atyray operating division.
  • Karaozek – Kyzylorda, with the length of 20 km for Kyzylorda operating division.

It should be noted, that from the beginning of track work season the Western Directorate have already successfully completed laying track panel on section Akkum – Talap, Bessaryk – Sauran for a total of 26 km and on section Kigash – D. Nurpeysova Passing loop – Passing loop 4 for a total of 19 km.

Let's keep that up! Renewing of track will allow improving the technical condition of sections, increase traffic safety and accelerate the speed of passenger and freight trains.