We congratulate the team of Integra Construction KZ LLP with the start of track works in 2021. Today the first track possession has been successfully carried out
The team of the Western Directorate renewed 1.181 km of track at Passing Loop 3 – Ustyurt section of Mangistau division.
During the overhaul season, our branches will have to improve 275.3 km of track in Almaty, Kostanay, Karaganda, Mangistau and Atyrau divisions.
- Western Directorate - 74,4 km
- Northern Directorate - 75,9 km
- Southern Directorate - 124,9 km
Focus on fulfilling the plan on time in compliance with the requirements of HSE! At the end of the season, we will determine the best teams and workers in terms of performance indicators. Good luck everyone!