The first technological "window" was held at Kunshash - Karagalinskaya site in the northern region of Kazakhstan in 2025. 1.2 km of the sleeper rail was updated in 8 hours. The work covered Kostanay road.
There is a lot of work ahead to upgrade the region's railway infrastructure. This year, the Northern Directorate will overhaul 97.2 km of railway track:
▪ 40 km – for Kokshetau road
▪ 8,1 km for Yessil road
▪ 49 km for Kostanay road
We congratulate to the branch team on the commencement of the track work and wish them a steady pace!