Skip to main content
We are building for
the good of society!
The laying of the track on Moiynty - Kyzylzhar line has begun
| News

The laying of the track on Moiynty - Kyzylzhar line has begun


On the construction of the new Moiynty-Kyzylzhar railway line, where Integra Construction KZ is the general contractor, one of the key stages has started - laying the rail-sleeper grid.

The work is carried out in accordance with the approved schedule, with the participation of 13 contractors. Since May of this year, more than 85% of the roadbed has been completed. The total length of the construction is 323 km.

To date, the first kilometer of the rail-sleeper grid has been laid, then laying will be carried out continuously along the entire length of the site.

The laying is being carried out by the Southern Directorate branch, using specialized equipment and specialists.

On October 28, a switch was installed at Kyzylzhar station, allowing further track laying to continue along the construction site. Moiynty-Kyzylzhar project is of great strategic importance for Kazakhstan - it will strengthen the transport connectivity of the regions.

Congratulations to the team and everyone involved on the start of track laying and wish them every success!

© 2009-2026 «Integra Construction KZ» LLP All rights reserved. | Website development: arctika.kz