The team of Northern Directorate has started track work
| News

The team of Northern Directorate has started track work


The first technological “window” in 2024 in the north region of Kazakhstan was held today at Kostanay-Alkau station.

In 6 hours of work, 1.2 km of rail-sleeper grid was renewed.

According to the plan, Northern Directorate will overhaul 114.9 km of railways this year. Of these, for Kostanay branch of the road – 60.7 km, for Kokshetau branch of the road – 54.2 km.

We wish everyone involved in the complex and important process of improving the country's railways the best of luck and great production victories.