• Northern Directorate updated 114.9 km of track.
• Western Directorate laid 112.8 km of railway.
Directorate team also restored 20.8 km of station tracks for Atyrau and Kyzylorda roads.
In general, the company's branches restored 227.7 km of track for Kokshetau, Kostanay, Atyrau and Kyzylorda roads.
Our team of professionals successfully coped with the task ahead of schedule.
In particular, at the sites: "Kokshetau-Petropavlovsk" — for 26 days; "Kokshetau-Zhanaesil" — for 17 days; "Zhanaesil-Kostanay" — for 10 days; "Sagiz-Makat" — for 35 days.
Congratulations to all participants on completion of laying work. We wish them new victories in 2025!