Road construction activities are in process in the southwestern residential area (No. 8 and No. 9) in Taldykorgan city.
Improvement of the territory, installation of a granite curb, side stones (curb), spillways, irrigation flumes are in the active phase. The energy sector along Balapanov and Bulvarnaya project streets is in process. The main passages on the pavement are 90% ready. This is a 6m wide dual carriageway.
“It is planned to commission the facility in 2024. The total length of roads is 5.5 km. According to the plan of the current year, we will complete the main passages: No. 1,2,3,4, as well as the main street Balapanov, Bulvarnaya and street No. 1. Previously, we completed activities related to protection sewerage networks, communications, external gas supply networks, erected small artificial structures,” said Timur Zhanuzakov, project manager.