200km mark is passed!
| News

200km mark is passed!


Shortly before the Transport Workers’ Day, a track possession for laying 1.5 km railway was held on Chaglinka-Zhaman-Aschi Section by the Northern Directorate.

Therefore, total plan implementation in different regions of Kazakhstan reached beyond 200 km. It’s a wonderful gift for the professional holiday!

From the beginning of works in 2023, completed scope of work by branches is as follows: Western Directorate – 99.8 km, Southern Directorate – 61.3 km, Northern Directorate – 39.7 km. Our managers, mid-level managers, operators, track workers, drivers, maintenance staff and all relevant persons once again showed their professionalism and excellent result.

Congratulations to the team of Integra Construction KZ with the professional holiday and wishes of new victories!